Bond Program by School:Quantum Academy Modernization Projects

Quantum Academy–Front of School

Series A work scope includes upgraded WiFi and wired networking equipment, upgraded copper and fiber cabling, improved electrical and environmental systems.

95% Complete


Series A work scope includes minor tenant improvements and the addition of a science lab to support a total of 320 students.

 

The Plans

plans showing the addition of a building and improvements to the Quantum Academy campus

Plans for Quantum Academy

 

Addition of Three New Classrooms

Quantum Academy Pool (before)

Quantum Academy Pool (before)

Backfill and Compacting Where the Pool House Was

Backfill and Compacting Where the Pool House Used to Be

Quantum Academy Pool (after)

Quantum Academy Pool (after)

Quantum Academy classrooms under construction

Three new classrooms near completion.

Classrooms building with gray stucco surrounded bu scaffolding

New classrooms with a new coat of stucco

painters applying a fresh coat of tan paint

New classrooms getting a fresh coat of paint

Construction workers working on the rooftop of the new classrooms

A view from the rooftop of the new classrooms.

interior of a classroom with stack of ceiling tiles

Interior of one of the new classrooms ready for ceiling tiles

interior of classroom will unfinished floor and ceiling tiles installed

Interior of one of the new classrooms

 

New Lunch Area

concrete slab for the new outside lunch area

Concrete surface of new outside lunch area

 

NEW FIRE LANE AND WATERLINE

Map of the new fire lane between Orange Glen Elementary and Quantum Academy

Map of the new fire lane between Orange Glen Elementary and Quantum Academy

construction workers working in a trench hooking up a water line

Hooking up new water line for fire safety

construction worker working in a trench hooking up a water line

Hooking up new water line for fire safety

New water valve for fire safety

New water valve for fire safety

Fire lane with fresh blacktop and painted red lines

The new fire lane between Quantum Academy and Orange Glen Elementary

Fire lane with fresh blacktop and painted red lines

New fire lane between Quantum Academy and Orange Glen Elementary 

 

New Medical Therapy Unit

The new medical therapy unit building being lowered by crane into its new location.

The new medical therapy unit building being lowered by crane into its new location.

New medical therapy unit near completion.

New medical therapy unit–Almost ready!

 

Upgraded Interior Spaces

Quantum Academy Corridor (before)

Quantum Academy Corridor (before)

Quantum Academy Corridor (after)

Quantum Academy Corridor (after)

Removal of All Interior Walls (5, 6, 7 & 8)

Removal of All Interior Walls (Old Rooms 5, 6, 7 & 8)

Interior Work

Interior Work

New Classrooms 5, 6 and 7 Framed

New Classrooms 5, 6 and 7 Framed

Quantum Academy – Classroom Expansion

Quantum Academy – Classroom Expansion

Exterior Concrete At New Lounge Location

Exterior Concrete At New Lounge Location

Demolition of Existing Lounge

Demolition of Existing Lounge