Bond Program by School: Felicita Elementary Modernization Projects

Classrooms
Series A work scope includes removal of some relocatable classrooms at some sites.
Room 34

Felicita Room 34

Removal of Room 34

Room 34 fully removed
Rooms 32 and 35

Getting ready for removal

Up on blocks–ready to be removed

Rooms 32 and 35 removed

Rooms 32 and 35 removed
Technology Infrastructure
Series A work scope includes upgraded WiFi and wired networking equipment, upgraded copper and fiber cabling, improved electrical and environmental systems.
90 percent complete

New Networking at Felicita